The short answer
A flat bought before its completion certificate carries GST of 5% of the total price, or 1% if it is an affordable home, with no input tax credit for the builder. Affordable means a carpet area of up to 60 square metres in the metropolitan areas named in the rules, or 90 elsewhere, and a price of no more than ₹45 lakh. A flat sold after the completion certificate, with the whole price received after it, carries no GST.
The two rates
| Flat | GST on the total price |
|---|---|
| Affordable residential apartment | 1% |
| Any other residential apartment | 5% |
Both are effective rates on the whole price. The law treats a third of the price as the value of the land, which carries no GST, and taxes the rest at a higher rate that works out to 1% or 5% of the total. The builder cannot set input tax credit against either, which is why they are lower than the 8% and 12% charged before April 2019.
What counts as an affordable home
Both conditions have to be met.
- A carpet area of up to 60 square metres in a metropolitan area, or up to 90 square metres anywhere else, villages included.
- A price charged by the builder of no more than ₹45 lakh.
- The metropolitan areas are Bengaluru, Chennai, Delhi NCR (Delhi, Noida, Greater Noida, Ghaziabad, Gurgaon and Faridabad), Hyderabad, Kolkata and the whole Mumbai Metropolitan Region.
When there is no GST
GST applies to the construction of a flat for sale. Once the completion certificate is issued, or the building is first occupied if that comes sooner, a flat sold with the whole price received after that date is the sale of a building, which GST does not reach. A completed flat resold by its owner carries no GST for the same reason.
A worked example
Three flats, each bought under construction. Pune is not one of the named metropolitan areas; Thane is part of the Mumbai Metropolitan Region, which is.
| Flat | Carpet area | Price | Rate | GST |
|---|---|---|---|---|
| Pune | 75 sq m | ₹60,00,000 | 5% | ₹3,00,000 |
| Pune | 85 sq m | ₹40,00,000 | 1% | ₹40,000 |
| Thane | 62 sq m | ₹40,00,000 | 5% | ₹2,00,000 |
The first flat costs more than ₹45 lakh, so it is not affordable whatever its size. The second is under both limits. The third costs the same as the second but is two square metres over the 60 square metre limit for a metropolitan area, which moves it from 1% to 5% and adds ₹1,60,000 of GST.
How it is paid, and what it does to the true cost
GST is charged on each demand the builder raises, so it is paid in step with a construction-linked plan rather than in one sum at the end. Like every instalment, the GST paid years before possession ties up money that would otherwise earn a return or reduce a loan, which is part of a flat’s true cost.
Terms in this guide
Sources
- Frequently asked questions on the real estate sector (GST rates from 1 April 2019) GST Council
- Press release on the 34th meeting of the GST Council: rates for residential real estate GST Council and the Press Information Bureau